Here's a quick review of the work that's being done to respond to the incident in Roseland. As of today (Thursday, August 28, 2025), the following tasks are complete:
**Construction of containment berm around the facility
**Approximately 820,000 gallons of product retrieved to this point
**5,717 barrels from the site
**213 barrels from the water
**726 barrels of raw product removed from the plant
**13,400 ft of containment boom deployed
**4 Marco skimmer boats deployed
**5 drum roller skimmer sets
**187 bails of absorbent boom deployed
**207 bails of absorbent pads deployed